research project

And Suddenly, Floors!

Upon returning to Newbern, the team continued the metal theme and spent the first day back coating all of the metal elements of the pod with a clear lacquer finish to prevent weathering while maintaining the unfinished look of the metal. Then they made the switch back to working with wood.

With all of the wood for the floors prepped and ready to go, installing the floors was a simple and quick process. Of course, before the wood could be placed, the world’s most substantial termite shields had to be installed. The termite shields comprise of ¼” steel plate welded into a box and are designed to complement the massiveness of the mass timber and concrete foundations.

After the termite shields were siliconed in place, the wood for the floors was placed, a process which took about fifteen minutes. Then the wood was roughly aligned so that the threaded rods could be inserted. Once the rods were in place and lighted fastened, the wood received its final alignment. By far the most time consuming part of this process was tightening the threaded rods as, even with our preliminary tightening, the wood still had subtle warping and cupping that needed to be squished out. The floor installation overall took about five hours, four of which went into tightening the threaded rods.

Stay tuned for the rest of the pod coming after Christmas.

Building is getting serious,

The Fabulous Floor Folk

Soundtrack: Construction Site Song | The Kiboomers

Steel Fabrication

The steel for the spreader angles and plates has been delivered and the team has been working on fabricating those pieces. The plates and angles will run along the walls, floors, and ceilings edges in order to evenly spread the load throughout the wall/floor/ceiling when the threaded rods are tightened down. Each plate and angle has to be cleaned, holes torched, and then coated with a sealant to prevent weathering. Once the steel is finished, the team can begin processing the wood for the walls and ceilings using those plates and angles as templates. 

As the pod begins to become a reality, the issue of properly staging the construction process to be as efficient as possible is becoming an important topic. To that end, the team decided to fabricate the trusses before beginning to build the pods so that the roof can be immediately installed once the walls and ceiling are in place to prevent the wood from being exposed to the environment for any length of time. It is to this end that Jim Turnipseed and Turnipseed International have been extremely helpful in this process. Not only was all of the steel for the project donated but the team was also able to use Turnipseed International’s welding shop to fabricate the trusses and other steel elements of the project. It was a welcome break from the wood processing to learn about steel and how to weld.

The whole process only took about 5 days. The team spent the first two days cutting down all the members of the trusses, the purlins, the runners, and the plates. The next day, with the help of the men working at the shop, they laid out the truss design on the warehouse floor and welded together a jig. This allowed the team to easily slide the members of the truss in place then weld together each joint. 2 days later, 11 trusses were completed and transported back to Newbern!

Stay tuned for updates as the team returns to Newbern and puts this steel to good use!

Already missing the shop,

The Metalworking Massers

Soundtrack: Dirty Paws | Of Monsters and Men

Horizontal and Vertical Sock Tests

Wondering if the team still masquerades as scientists? Don’t worry, the science lives on. Throughout the construction process, the team has been running horizontal sock tests day and night; four tests a day, every day but Sundays! They have completed a series of small scale horizontal sock tests and are currently working on their first peer reviewed paper. This paper will present their findings on the suitability of wood for Breathing Walls, as well as their initial findings on their vertical sock tests.

Horizontal sock testing set up

Vertical sock testing is the next step in the testing series. As the team scales up the tests, a new variable is added. This series of tests will introduce buoyancy ventilation to the system rather than use forced air with the blower door fan. The sock, currently set up in the team’s living room, is an 8’ tall insulated cone with sensors at the top and bottom logging pressure, temperature, air flow, and humidity. They are currently calibrating this test and hope to finish up the series before Christmas! After that, they’ll move on to laminated panels and eventually to testing the full-size building currently in construction.

The team is off to the big city (Birmingham) again soon to trade off with the Horseshoe Hub Courtyard team in the metal shop. They’ll be taking a rare break from wood and fabricating trusses and other steel components, so stay tuned for updates.

Full of hot air,

The Testing Team

Soundtrack: The Scientist | Coldplay

Laying the Groundwork

The concrete curbs are cured, the formwork deconstructed, and the gravel laid. The site went from a muddy mess to a modern art installation in just a few days with the addition of four concrete monoliths and a field of compacted gravel. Next the team plans to install the termite shields, which are currently in the process of being fabricating, and then construct the floors!

In other exciting news, all the wood for the floors is prepped and ready to go! The team planed, ripped, chopped, and drilled 122 pieces of true dimension 2×8 timber. After ascertaining the scale of this endeavor, they decided to call around and see if any local mills could help them out with the planing and ripping process. Howard Custom Lumber is currently processing the wood for the walls and ceilings (over 700 pieces of wood!) to save the team a little bit (actually a lot) of time.

While the floors were being installed and wood being processed for the walls and ceilings, the team did a quick structural test on the mass timber loft. On a rainy Friday afternoon, they constructed the loft and loaded it up to make sure it wouldn’t deflected when supported on the extreme edges. The mock up was a success, and the loft design is moving forward.

Stay tuned for the heroic return of the wood and its eventual transformation into the first ever Breathing Wall Mass Timber pods!

Sore from moving all that lumber,

The Fearless Foresters

Soundtrack: Graveclothes | Birdtalker

Of Local Interest

Howdy from the new center for Thermal Mass and Buoyancy Ventilation Research in Newbern, Alabama!

The team is fresh off their first presentation with reviewers Kim Clements and Joe Schneider. Kim and Joe are the founders of J.A.S. Design Build in Seattle, Washington. They helped the team develop a clearer way to explain the thermal mass and buoyancy ventilation theory.

The team reviewing the review on Monday morning.

Eventually, the team will be publishing a paper, with their partners at McGill University. The paper will aim to speak to architects and builders who could implement the thermal mass and buoyancy ventilation system in their buildings. Reviews with folks like Kim and Joe will help the team learn how to communicate best with the design and construction world.

The chosen materials, their components, and their processing

Besides preparing for their first presentation, the team has been working on material research. A crucial part of the Thermal Mass and Buoyancy Ventilation Research Project is understanding the embodied energy of their construction materials. The team will study exactly what goes into the making of the materials from harvesting natural resources to transporting the finish material to the construction site. Timber, brick, rammed earth, and concrete are the materials the team are considering for the thermal masses. To limit energy lost to transportation and as an investment in Alabama, the team is investigating local material manufacturers within the state.

Speaking of local, here in Newbern, the Hurricane Lilies are still in bloom, Rural Studio students are stealing all the sunshine, and a shark must have been spotted downtown. From the T.M.B.V. Research Project Team to you, keep it real and real local!